High Point High School

Status
Planning
Funding Model
Traditional
Project Type
Replacement
Budget
$189,000,000
Architect
Grimm + Parker Architecture
General Contractor
TBD
Project Manager
Anoop Gupta

School Information

Principal
Dr. Lori Taylor
Address
3601 Powder Mill Road, Beltsville, MD 20705
Neighborhood
Beltsville, Calverton
School Board District
District 1
County Council District
District 1
State Legislative District
District 21

Project Timeline

Project Scope

Replacement of the existing 318,376 SF,2081-seat high school with a new 423,000 SF high school on the same site with a capacity of 2600 students.

News & Announcements

There are currently no announcements for this project.

Project Updates

February 2024

Past Month's Accomplishments

  • Planning funds were approved by the State of Maryland to finalize educational specifications and begin architectural design.
  • Development of the educational specifications commenced.
  • Meetings with PGCPS instructional leadership to confirm programs were held.

February Lookahead

  • Educational specifications will be finalized and reviewed with all parties before sending to the Board of Education for approval.
  • Discussions with permitting agencies will continue.
  • Application for funding will continue.
  • The design phase will begin.

November 2023

Past Month's Accomplishments

  • Planning funds were approved by the State of Maryland to finalize educational specifications and begin architectural design.
  • Development of the educational specifications commenced.
  • Meetings with PGCPS instructional leadership took place to confirm programs.

Next Month's Lookahead

  • Educational specifications will be finalized and reviewed with all parties before sending to the Board of Education for approval.
  • Discussions with permitting agencies will continue.
  • The application process for funding will continue.
  • The design phase will begin.

Documents & Presentations

Project Information Town Hall - 11/06/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Feasibility Study Update - 05/03/2019 | Feasibility Study

Board Approval of Feasibility Study - 06/12/2014 | Board Action Summary

Feasibility Study - 05/12/2014 | Feasibility Study