Central High School HVAC Renovation

Scope of Work

Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls.

Project Details

  • Budget: $20,218,000 
  • Planning/Design Start: 2016 
  • Construction Start:  March 2020
  • Phase & Percentage Complete: Construction; 95%
  • Current Status: Substantial completion achieved- school in function. 
  • Upcoming Activities: Final close out items in progress: final inspections and training.
  • Project Team:
  • PGCPS Contact: Anoop Gupta, Project Manager